NCLT panel says Jaypee Infratech failed to deliver projects within the promised
SENSEX 74,315.61 + 1,533.72 NIFTY 22,997.35 + 374.65 CRUDEOIL 9,270.00 + 154.00 GOLD 147,484.00 + 1,636.00 SILVER 210,700.00 + 2,362.00 SENSEX 74,315.61 + 1,533.72 NIFTY 22,997.35 + 374.65 NIFTY 22,997.35 + 374.65…

+ 1,533.72
NIFTY 22,997.35+ 374.65
CRUDEOIL 9,270.00+ 154.00
GOLD 147,484.00+ 1,636.00
SILVER 210,700.00+ 2,362.00
SENSEX 74,315.61+ 1,533.72
NIFTY 22,997.35+ 374.65
NIFTY 22,997.35+ 374.65
CRUDEOIL 9,270.00+ 154.00
CRUDEOIL 9,270.00+ 154.00
GOLD 147,484.00+ 1,636.00
'; } document.getElementById("lgdv").innerHTML = htmlElements; } function numberformat(i) { return Number(parseFloat(i).toFixed(2)).toLocaleString('en', { minimumFractionDigits: 2 }) } async function gatherResponse(response) { const { headers } = response; const contentType = headers.get('content-type') || ''; if (contentType.includes('application/json')) { return await response.json() } return response.text(); } function getWidth() { if (Math.max(document.body.scrollWidth,document.documentElement.scrollWidth,document.body.offsetWidth,document.documentElement.offsetWidth,document.documentElement.clientWidth) > 991) { document.getElementById("mob").style.display = "none"; document.getElementById("lgdv").style.display = "block"; } else { document.getElementById("mob").style.display = "block"; document.getElementById("lgdv").style.display = "none"; } } getWidth(); THIS AD SUPPORTS OUR JOURNALISM. SUBSCRIBE FOR MINIMAL ADS.THIS AD SUPPORTS OUR JOURNALISM. SUBSCRIBE FOR MINIMAL ADS.Homebuyers’ grievances over construction delays and non-delivery were “correct and genuine” and NCLT has to take “urgent cognizance” of the lapses and issue appropriate compliance directions
By Ankita Upadhyay
Updated - October 15, 2026 at 11:57 PM.A fact-finding committee appointed by the National Company Law Tribunal (NCLT) has concluded that Jaypee Infratech Ltd (JIL), taken over by a consortium led by Suraksha Realty Limited under an approved resolution plan, failed to complete projects within the promised timelines, leaving thousands of homebuyers waiting for possession.
The two-member committee, comprising former NCLT Members Prasanta Kumar Mohanty and Dr Deepti Mukesh, submitted its final report on August 20, covering the progress of all 19 JIL projects as of June 30, 2026.
It found that homebuyers’ grievances over construction delays and non-delivery were “correct and genuine” and urged the NCLT to take “urgent cognizance” of the lapses and issue appropriate compliance directions.
The NCLT had approved the resolution plan submitted by Suraksha Realty Limited and Lakshdeep Investments and Finance Private Limited in March 2023, a decision upheld by the National Company Law Appellate Tribunal (NCLAT) in May 2024. The consortium subsequently took charge of JIL.
Of JIL’s 250 residential towers, 91 comprising 12,867 units had been completed before the successful resolution applicant (SRA) took charge. The remaining 159 towers comprise 97 stalled towers with 10,164 units and 62 near-complete towers involving 6,067 units.
The SRA was required to complete the residual work on the 62 near-complete towers within 18 months, including the six-month period and one-year grace period. However, over two years, it issued 3,444 offers of possession and executed 2,614 sub-lease deeds. The committee said more than 6,000 offers could have been issued if the obligation had been met.
Progress on the 97 stalled towers, meanwhile, could not be independently verified, with the committee saying the SRA’s data lacked credibility.
Labour shortfall
The committee identified inadequate labour deployment as one of the principal reasons for the delays. The resolution plan envisaged about 12,000 labourers, but the SRA reported an average deployment of 1,787 workers in January-March 2025, 4,735 in January-March 2026 and 5,415 in April-June 2026.
During site visits, however, the committee observed only 200-300 workers at some locations and estimated actual deployment at around 3,500-4,000. It rejected the SRA’s contention that more than 5,000 workers were neither required nor available, saying the position was “neither acceptable nor credible”. It recommended deploying 12,000 or more workers immediately.
The panel also found homebuyers’ concerns over the quality of steel being used to be genuine. It noted that steel other than that supplied by manufacturers such as SAIL and Tata was being used and stressed that quality could not be compromised in 30-32-storey towers located in an earthquake-prone area.
The report flagged several other breaches, including the failure to arrange a Rs 3,000 crore working-capital facility required under the resolution plan. It also found that three instalments totalling Rs 666 crore towards additional farmer compensation ordered by the NCLAT remained unpaid as of May 24, 2026.
The committee further noted that monthly progress reports mandated by the NCLT had not been filed since the SRA took over in June 2024. It described the Project Monitoring Committee as “ineffective” and said funds earmarked for construction had been diverted to associate entities and invested in mutual funds. An FIR registered in January alleges diversion of about Rs 300 crore; the SRA has said the transactions were subsequently reversed.
Suraksha exit questioned
The committee also questioned the departure of Suraksha Realty, one of the two resolution applicants. In an affidavit, the SRA said Suraksha had been “duly discharged” and had no role in implementation, leaving Lakshdeep Investments and Finance Private Limited to carry out the plan.
The committee said the circumstances of the exit lacked clarity and noted that the resolution plan made both applicants jointly and severally responsible. It found it “surprising” that one applicant could withdraw without informing stakeholders or seeking the tribunal’s clearance while the plan remained unimplemented. It also said it was unclear whether Suraksha was still associated with JIL when the alleged diversion of funds occurred.
Delays were also reported in villas, plots and commercial units. At Kingswood Oriental, seven of 37 villas remained incomplete, while only 18 possession offers had been issued for 652 commercial units across three projects.
The committee also backed plot allottees at Agra Kensington Park, where the SRA had scrapped development and offered refunds. After inspecting the 850-acre site, it found the land well located, without encroachment, and said the SRA should allot the plots “without loss of time.”
No fresh resolution plan
The committee identified interest, penal charges and transfer fees as another major grievance. It said no interest or penal interest should be charged for the insolvency moratorium period between August 9, 2017 and June 4, 2024, when banks did not disburse loans. It also recommended resolving transfer-charge issues, saying this could benefit more than 10,000 buyers.
Despite its findings, the committee advised against inviting fresh resolution plans, noting that construction and deliveries were continuing, although not strictly according to the approved timelines.
Instead, it recommended restructuring the monitoring mechanism. This includes reconstituting the Project Monitoring Committee within a month, appointing an Independent Observer to the JIL board, renewing the Rs 100 crore performance bank guarantee through February 2028 and allowing lenders to sell allotted land parcels transparently.
The SRA told the committee that there was no shortage of funds, citing Rs 1,403 crore in cash and equivalents as of March 31, 2026, along with expected hospital-sale proceeds of about Rs 600 crore and monthly toll collections of Rs 50-60 crore from the Yamuna Expressway. However, the committee found the claim of adequate funds unconvincing in view of the slow construction, labour shortfall and unpaid YEIDA instalments.
The decision on penalising the SRA or taking any stronger action now rests with the NCLT.
Published on October 6, 2026
THIS AD SUPPORTS OUR JOURNALISM. SUBSCRIBE FOR MINIMAL ADS. THIS AD SUPPORTS OUR JOURNALISM. SUBSCRIBE FOR MINIMAL ADS. THIS AD SUPPORTS OUR JOURNALISM. SUBSCRIBE FOR MINIMAL ADS. THIS AD SUPPORTS OUR JOURNALISM. SUBSCRIBE FOR MINIMAL ADS.Sign into Unlock benefits!- Access 10 free stories per month
- Get notified by email for early preview to new features, discounts & offers
Figures reflect the source report and its stated period. This article is for information and is not investment advice.